Carbotura · Advanced Circular Manufacturing · Feedstock System Assessment

Regina–Moose Jaw Corridor
Feedstock System Assessment

The corridor's ~400 TPD of landfill-bound feedstock flows to two municipally operated sites under an accelerating disposal cost trajectory, with Moose Jaw's current facility reaching end-of-life by 2030 and no approved replacement site confirmed as of March 2026.

Document: Stage 1 Feedstock System Assessment Prepared for: Regina–Moose Jaw Corridor, Saskatchewan Prepared by: Carbotura, Inc. Date: March 2026 Standard: PSAB
Total Addressable Feedstock
~400
TPD planning basis Estimated
Corridor Population
~323K
persons, 2026 estimate Estimated
Regina Tipping Fee
$95
CAD/tonne Verified
Moose Jaw Landfill Life
~4 yrs
remaining to ~2030 Verified
New Landfill Capital
$133M
CAD — no site approved Verified
EPCOR WWTP Contract
2044
expiry — Regina WWTP Verified
§0

ACM Capability Declaration

■ ACM Capability Finding — Required Disclosure

Advanced Circular Manufacturing processes all material streams the Regina–Moose Jaw Corridor generates. The ACM platform accepts mixed municipal feedstock, organics, recyclables, industrial and commercial streams, biosolids, construction and demolition materials, and special waste streams including PFAS-containing materials. Addressability of each stream is determined exclusively by access constraints — regulatory, contractual, or logistical. Capability limitations do not apply to any stream in this assessment.

This document is a diagnostic assessment. Its function is to define the corridor's current feedstock system — volumes, costs, operators, and structural pressures. The Assessment does not advocate for a course of action, model royalty outcomes, or imply disposition of any stream. It records what is known, what is estimated, and what remains unconfirmed.

Source-type indicators appear throughout this document. Verified — confirmed from public records or official sources. Estimated — derived from available data with stated assumptions. Not yet confirmed — data gap requiring Term Sheet phase verification. Access classification values reflect logistical and contractual access — not processing capability.

Regina–Moose Jaw Corridor · Manufacturing Feedstock System Overview
§1

Feedstock System Overview

§1.1 Stream Inventory and Access Classification

The corridor encompasses two independent municipal feedstock disposal systems — the City of Regina and the City of Moose Jaw — with seven surrounding communities directing volumes primarily to the two city facilities. Combined, the corridor generates approximately 390–450 TPD of non-construction-and-demolition feedstock streams, and an additional ~195 TPD of construction and demolition material on a seasonal basis.

Stream Jurisdiction Est. TPD Est. TPY Access Classification Source Basis
Residential garbage (mixed, brown cart) City of Regina 149 Estimated 54,400 IMMEDIATE Waste Plan Regina 2023
Organics — food & yard (green cart) City of Regina 66 Estimated 24,000 IMMEDIATE City of Regina Food & Yard Waste Service data
Dry recyclables (blue cart) City of Regina 16 Estimated 5,800 IMMEDIATE Waste Plan Regina 2023
ICI waste (non-residential) City of Regina Not yet confirmed IMMEDIATE Bylaw active Jan 2028; volumes unconfirmed
Biosolids (WWTP-derived) City of Regina / EPCOR Water Services Inc. Not yet confirmed CONDITIONAL EPCOR contract to 2044; commercial engagement required
Construction & demolition (C&D) City of Regina ~195 Estimated ~71,200 CONDITIONAL 2013–2020 historical average; seasonal/intermittent
All landfill-disposed streams City of Moose Jaw ~106 Estimated ~38,600 IMMEDIATE Moose Jaw council data, H1 2025 annualised
Organics (embedded in Moose Jaw stream) City of Moose Jaw ~35 Estimated ~12,800 IMMEDIATE SWRC ~1/3 share estimate; no curbside program
All streams — corridor communities White City, Pilot Butte, Balgonie, Pense, RMs ~22 Estimated ~8,000 IMMEDIATE Per-capita derivation; 21,000 pop.
Total addressable (non-C&D) Full corridor ~390–450 Estimated ~142,000–164,000 Planning basis: 400 TPD
▶ Planning Basis Note

400 TPD is the deployment planning basis for all downstream analysis. This figure excludes C&D (classified CONDITIONAL) and unconfirmed ICI volumes. Biosolids are excluded from the planning basis pending EPCOR commercial engagement. ICI data gap: Regina's ICI bylaw takes full effect January 2028; separate ICI tonnage has not been published. These streams are classified IMMEDIATE on access confirmation and will expand total addressable feedstock materially above 400 TPD when confirmed. Seasonal variation of ±25% applies to organics and yard waste streams due to Saskatchewan climate.

§1.2 Feedstock Volume Distribution
Corridor Feedstock Streams — Planning-Basis TPD
Regina residential garbage represents the single largest confirmed stream at 149 TPD; Moose Jaw's combined volume (~106 TPD) is prioritised for Phase Initial deployment given landfill urgency.
Source: Waste Plan Regina 2023; City of Moose Jaw council data H1 2025; SWRC estimates. All values ESTIMATED unless noted. C&D excluded from planning basis.
§1.3 Feedstock Infrastructure — Key Nodes
Facility Verified Operator Role Location Status
Fleet Street Landfill City of Regina Verified Primary disposal — Regina streams Northeast Regina Active
Regina Wastewater Treatment Plant EPCOR Water Services Inc. Verified
formerly EPCOR Saskatchewan Water Partners Inc.
Wastewater treatment; biosolids generation and storage West of Regina, Wascana Creek corridor Active · Contract expires June 2044
SK Recycles Material Recovery Facility SK Recycles Verified Blue cart recycling processing — Regina Regina area Active from July 1, 2025
Temporary Organics Processing Site City of Regina Verified Organics processing — transitional Fleet Street Landfill site Transitional — EverGen contract terminated Jan 2025; Awasis project pending
Caribou Street East Sanitary Landfill City of Moose Jaw Verified Primary disposal — Moose Jaw and corridor Moose Jaw east Active · End-of-life ~2030 · No replacement approved
Moose Jaw Wastewater Treatment Plant City of Moose Jaw Verified Wastewater treatment; WWTP headworks upgrade underway North Moose Jaw — adjacent to proposed new landfill zone Active · Lift station replacement $26.6M 2023–2025
Buffalo Pound Water Treatment Plant Buffalo Pound Provincial Water Supply Commission Verified Potable water supply — both cities and corridor (~260,000 persons) Highway 2 corridor, near Moose Jaw Active · Progressive Design Build upgrade underway
Executive Implications — §1
  • The operator landscape is stable for Regina: EPCOR is contracted to June 2044 for the WWTP; SK Recycles assumed the recycling processing contract July 1, 2025 at lower cost, reducing household utility fees from January 2026.
  • Moose Jaw's waste system is in structural transition: the current landfill has approximately four years of remaining capacity, no replacement site has been approved, and the Ministry of Environment has declined site expansion. This transition window is the dominant structural pressure in this corridor.
  • Regina's organics processing is in active gap status: the EverGen contract was terminated January 2025 after RM of Edenwold rejected the composting facility application. The Awasis replacement contract is in early stages. 24,000 TPY of organic feedstock has no confirmed long-term processor.
§2

Current Disposal Cost Analysis

§2.1 Tipping Fee Structure
Jurisdiction Tipping Fee — Residential Tipping Fee — Non-Resident Classification Source
City of Regina $95.00 CAD/tonne $95.00 CAD/tonne Verified City of Regina Landfill schedule, verified Oct 2025
City of Moose Jaw $90.00 CAD/tonne $100.00 CAD/tonne Verified Moose Jaw Budget 2024, verified Dec 2023
Corridor weighted average ~$93.50 CAD/tonne Estimated Population-weighted blend (Regina 81%, Moose Jaw / corridor 19%)

Both cities have implemented annual tipping fee escalation strategies. Moose Jaw explicitly benchmarks against Regina rates to maintain competitive positioning — creating a structurally linked cost trajectory across the corridor. Regina moved waste collection fully to user-pay from January 1, 2024; household annual fees are $149.65–$240.90 CAD (all-in, three carts). Moose Jaw charges $30.87 CAD/household per quarter ($123.48/year).

§2.2 Full Weighted Disposal Cost (FWDC)

The FWDC represents the all-in cost per tonne of feedstock currently disposed of by the corridor — tipping fee plus transport and collection costs allocated per tonne. Transport cost per tonne has not been confirmed from public data; the planning-basis estimate is $15–35 CAD/tonne based on Saskatchewan rural/urban collection norms.

Cost Component Estimate (CAD/tonne) Classification
Corridor weighted average tipping fee $93.50 Verified
Transport and collection allocation per tonne $15–35 Not yet confirmed
FWDC — planning basis range ~$108–128 Estimated
▶ FWDC Disclosure

The FWDC will be confirmed during Term Sheet phase verification, which includes verified transport cost data. All financial modelling in subsequent documents uses the confirmed Beneficiation Fee of $100 CAD/tonne — set at the Carbotura standard floor by the sponsoring party — independently of FWDC derivation. The FWDC range above is diagnostic only and does not affect downstream financial projections.

§2.3 Cost Trajectory — 10-Year Escalation Outlook
Corridor Disposal Cost Trajectory — State A (Without ACM)
At 3% annual escalation (consistent with Moose Jaw's confirmed fee escalation policy), corridor tipping costs reach ~$125 CAD/tonne by Year 10. Moose Jaw new landfill capital ($133M CAD) adds a non-recurring structural cost event not reflected in this per-tonne view.
Source: Verified tipping fees; 3% escalation basis per Moose Jaw Budget 2024 policy. All projected values MODELED.
Executive Implications — §2
  • Moose Jaw's feedstock disposal cost trajectory is not a planning abstraction — it is a live operational constraint. The city has formally contacted the Ministry of Environment about waste-to-energy alternatives (June 2025). The Ministry responded that the current landfill site is not expandable and that a waste-to-energy framework had not yet been established.
  • The $133M CAD new landfill capital cost was confirmed by a commissioned concept design report presented to Moose Jaw City Council in July 2025. If constructed, this capital burden flows into the tipping fee structure over a 75-year service life — adding approximately $1.77M CAD annually in debt service alone at standard municipal financing rates.
  • Decision window: every month without a confirmed alternative advances the procurement clock on the $133M landfill capital commitment. When procurement is formally authorised, that capital obligation becomes irreversible. No indication of formal procurement authorisation as of March 2026.
§3

Biosolids Stream Analysis

The Regina Wastewater Treatment Plant — operated by EPCOR Water Services Inc. under a design-build-finance-operate contract expiring June 2044 — treats more than 25 billion litres of wastewater annually for a service area sized for a population of approximately 258,000. The facility uses biological nutrient removal with ultraviolet disinfection. Biosolids are generated through the solids treatment stream and stored in a repurposed lagoon on site.

The volume of biosolids generated in TPD has not been confirmed in public data. This is recorded as an unresolved data gap. At standard Canadian municipal biosolids generation ratios (approximately 30–60 kg dry solids per person per year), the Regina WWTP generates an estimated 20–40 TPD of dry biosolids — a material feedstock stream with high ACM processing value.

▸ Biosolids Access Classification: CONDITIONAL

Biosolids access classification is CONDITIONAL — not IMMEDIATE — because the EPCOR Water Services Inc. commercial relationship requires a separate engagement with EPCOR as the operating contractor and the City of Regina as facility owner. The City retains ownership of the WWTP; EPCOR operates and maintains it under the P3 contract. No contractual obstacle to a biosolids offtake engagement has been identified. The classification reflects the requirement to initiate commercial discussions — not a capability constraint on ACM processing.

Moose Jaw's WWTP is city-operated. Biosolids from this facility are classified IMMEDIATE on the same basis as other City of Moose Jaw-controlled streams. Moose Jaw WWTP is located in the north of the city, adjacent to the area identified by city administration as the preferred location for a new solid waste management facility — creating a natural co-location opportunity for biosolids and municipal feedstock streams at Phase Initial.

Executive Implications — §3
  • EPCOR's biosolids engagement is a Phase Expanded opportunity — not a Phase Initial dependency. Initiating the commercial discussion with EPCOR during Term Sheet negotiation preserves the option to include this high-value stream at full deployment.
  • Moose Jaw's co-located WWTP biosolids represent an IMMEDIATE-access stream that reinforces the Priority 1 site candidacy of the Moose Jaw WWTP precinct zone — detailed in the Proposal.
§4

System Transition Risks

§4.1 Moose Jaw Landfill End-of-Life
▲ Critical Infrastructure Risk — Confirmed

The Caribou Street East Sanitary Landfill has been in continuous operation for nearly 100 years. City administration has confirmed it will exhaust capacity by approximately 2030. Proposed replacement sites have encountered the following confirmed obstacles:

  • Rural Municipality of Moose Jaw rejected the first site application — June 2024
  • Ministry of Environment declined site expansion at the current location — confirmed in ministry correspondence to the mayor's office, June 2025
  • Three alternative sites under council review as of July 2025 — none approved
  • Airport zoning regulations restrict the city-owned WWTP-adjacent site; council voted 3-2 in July 2025 to seek an exemption — outcome pending

The $133M CAD concept design cost is confirmed for a 75-year, 3.75 million-tonne capacity new facility. Between 2021 and 2024, the Moose Jaw landfill collected 38,432–83,379 tonnes annually, generating $2.98M–$5.48M in tipping fee revenue annually. In H1 2025, the landfill collected 19,302 tonnes — consistent with the lower end of the annual range.

§4.1 Regina Organics Processing Disruption

The City of Regina terminated its contract with EverGen Infrastructure Corp. in January 2025 after the RM of Edenwold unanimously rejected EverGen's composting facility application in December 2023. Regina's 24,000 TPY of organic feedstock is currently processed at a temporary site at the Fleet Street Landfill — a bridging arrangement with no confirmed end date. A new organics processing contract has been issued (Awasis project, December 2025) and is in early stages. Until this contract is resolved, 24,000 TPY of organic feedstock has no confirmed long-term processor — making it an access-ready stream in active structural transition.

§4.3 Recycling Processing Transition

SK Recycles assumed the recycling processing contract from the prior processor effective July 1, 2025. The transition reduced processing costs sufficiently for the City of Regina to reduce household waste utility fees effective January 1, 2026. The SK Recycles contract is current; no disruption is indicated. This stream — approximately 5,800 TPY — is classified IMMEDIATE with confirmed volume.

§4.4 ICI Stream Activation (Regina)

Regina's ICI waste management bylaw requires all businesses, institutions, and organisations to implement multi-stream programs by January 1, 2028. The ICI sector diversion rate was first measured at 11% in 2024. As ICI waste volumes are confirmed and streams are formalised, the corridor's total addressable feedstock will expand materially above the 400 TPD planning basis. The City of Regina's Early Adopter Incentive Program reimburses 10% of capital investment in waste bins or processing technologies (up to $15,000 per entity) for businesses implementing programs by July 1, 2026 — indicating the City is actively driving ICI compliance ahead of the 2028 deadline.

Executive Implications — §4
  • The confluence of Moose Jaw's landfill crisis (no approved site, ~4 years remaining), Regina's organics processing gap (EverGen contract terminated, replacement pending), and the forthcoming ICI stream activation (2028 bylaw) creates a structural demand window for an ACM facility across this corridor. None of these three conditions is speculative — each is confirmed by council decisions, ministry correspondence, or city bylaw as of March 2026.
  • The ICI bylaw activation creates a hard-date demand event: by January 2028, businesses in Regina must have multi-stream programs in place. A Phase Medium ACM facility operational at T0+42 months can absorb this stream directly; without it, separate ICI processing contracts must be procured — layering additional utility cost onto the system at exactly the point ICI fees are being transitioned to businesses.
§5

Feedstock Composition Summary

The corridor feedstock is characteristic of Canadian Prairie municipal streams. Key compositional characteristics are based on Waste Plan Regina 2023 waste characterisation data and Saskatchewan Waste Reduction Council standards. Compositional data for Moose Jaw's mixed stream is derived from SWRC provincial benchmarks; no independent Moose Jaw-specific characterisation study has been identified.

Composition Category Estimated Share of Mixed Stream Access Classification ACM Note
Organic / putrescible 35–40% IMMEDIATE High conversion value; methane-generating when landfilled
Paper and cardboard 18–22% IMMEDIATE High carbon content; Regenesis™ Protocol feedstock
Plastics (all types) 12–16% IMMEDIATE All polymer types including non-recyclable grades
Metals 5–7% IMMEDIATE Circular Materials metal recovery stream
Glass 4–6% IMMEDIATE Mineral aggregate output pathway
Textiles and other 5–8% IMMEDIATE Polymer and fibre reforming
Inert / residual 8–12% IMMEDIATE Inert aggregate output
PFAS-containing streams (select categories) Present — embedded IMMEDIATE Addressed by anoxic elemental dissociation — see note
■ PFAS Note

Per- and polyfluoroalkyl substances (often called "forever chemicals") are present in this corridor's feedstock stream embedded within various consumer product and packaging categories. The ACM platform's anoxic elemental dissociation process — which operates without oxygen and without combustion — is designed to address PFAS-containing materials at the elemental level. The presence of PFAS-containing materials in the corridor feedstock does not constitute an access constraint or a capability limitation. It constitutes a regulatory communication consideration that is addressed in downstream engagement documents.

All compositions are Estimated from Waste Plan Regina 2023 characterisation data and SWRC provincial benchmarks. A site-specific waste characterisation study will be conducted during Term Sheet phase verification to confirm stream composition for ACM facility design parameters.

§6

Feedstock Infrastructure Map

The map below identifies the primary feedstock infrastructure nodes across the Regina–Moose Jaw Corridor. Node locations reflect verified facility positions. The corridor spans approximately 75 km along the Trans-Canada Highway 1 axis between Regina and Moose Jaw.

◎ Feedstock Infrastructure Map

Loading Google Maps — requires config.js API key

Fleet Street Landfill · Regina WWTP (EPCOR) · SK Recycles MRF · Caribou St Landfill · Moose Jaw WWTP · Buffalo Pound WTP

Landfill / disposal site
Wastewater treatment plant
Processing facility
Water treatment plant
Corridor Feedstock Infrastructure — Node Map
The 75 km Highway 1 corridor axis connects two independent municipal feedstock disposal systems. The Moose Jaw WWTP precinct (north Moose Jaw) and the Fleet Street corridor (northeast Regina) represent the two primary co-location candidates for ACM facility siting.
Source: Verified facility locations — City of Regina, EPCOR, City of Moose Jaw, Buffalo Pound Commission public records. Coordinates are planning-basis estimates confirmed at feasibility.
§7

Authoritative Glossary

This glossary is the authoritative terminology reference for the full Regina–Moose Jaw Corridor engagement suite. All documents in the suite use these definitions.

Advanced Circular Manufacturing (ACM)
Carbotura's integrated manufacturing platform that converts secondary material feedstocks into manufactured products using Microwave Catalytic Reforming and related protocols. ACM is not waste management, recycling, or waste-to-energy.
Anoxic elemental dissociation
The ACM process by which organic and polymer chains are disintegrated in an oxygen-free environment, preventing combustion and enabling elemental dissociation. Not incineration. Designed to address PFAS-containing streams.
Circular Supply Agreement (CSA)
The 30-year contractual instrument between Carbotura and the community governing feedstock supply, Beneficiation Fee payments, and Circular Royalty™ structure.
Circular Royalty™
The conversion royalty paid by Carbotura to the community, calculated as a percentage of the Year 1 Beneficiation Fee per tonne on a rolling monthly basis, commencing 13 months after the corresponding Beneficiation Fee payment.
EPCOR Water Services Inc.
Current operating entity of the Regina WWTP under a design-build-finance-operate model. Operating contract expires June 2044. City of Regina retains facility ownership. Formerly incorporated for this project as EPCOR Saskatchewan Water Partners Inc.
Feedstock
Materials supplied to the ACM facility for processing. In this corridor, feedstock includes all streams the community currently classifies as solid waste, organics, recyclables, biosolids, and industrial by-products.
Feedstock Hauler
Enclosed vehicles delivering feedstock to the ACM facility. The community's current collection fleet serves this function under the Circular Supply Agreement.
Full Weighted Disposal Cost (FWDC)
The all-in per-tonne cost of feedstock disposal to the community — tipping fee plus transport and handling costs. The basis for Beneficiation Fee derivation formula: TMC = MAX($100 CAD, MIN($150 CAD, FWDC − $5 CAD)).
ICI sector
Industrial, Commercial, and Institutional — the non-residential waste-generating sector in Regina, governed by bylaw from January 1, 2028.
Microwave Catalytic Reforming
The core thermal-catalytic process used in the ACM platform to convert feedstock into Circular Materials and energy vectors. Not combustion-based.
Modular ACM Factory
The physical facility structure. Each module has a design capacity of 100 TPD. Modules are deployed sequentially — Phase Initial (1 module), Phase Medium (2 modules), Phase Expanded (4 modules).
Near-zero landfill disposition
The ACM platform is designed for near-zero residual to landfill. This means the overwhelming majority of feedstock input is converted to manufactured materials or energy. Absolute zero is not claimed.
PFAS
Per- and polyfluoroalkyl substances — synthetic chemicals found in various consumer and industrial products. Present in this corridor's feedstock stream. ACM's anoxic process is designed to address PFAS at the elemental level.
Phase Expanded
Third deployment phase. 4 modules / 400 TPD capacity. Full corridor service. Commercial operations: T0 + 60 months.
Phase Initial
First deployment phase. 1 module / 100 TPD capacity. Priority: Moose Jaw. Commercial operations: T0 + 24 months.
Phase Medium
Second deployment phase. 2 modules / 200 TPD capacity. Full operations: T0 + 42 months.
Pregenesis™ Protocol
ACM feedstock preparation and sorting process preceding the primary conversion protocol. Also referred to as feedstock preparation.
PSAB
Public Sector Accounting Board. The applicable Canadian accounting standard for municipal and provincial government financial reporting. Governs this engagement for community-facing financial documents.
Regenesis™ Protocol
ACM's primary feedstock disintegration and conversion protocol. Also referred to as feedstock disintegration.
Circular Materials
Manufactured materials output from the ACM process. Includes RevCon™ 1 through 5 product grades. Not characterised as recycled materials, byproducts, or residuals.
SK Recycles
Current operator of Regina's recycling processing program, effective July 1, 2025. Assumed the contract from the prior processor at lower cost, enabling Regina utility fee reductions from January 2026.
Beneficiation Fee
Total Material Conversion Fee — the Beneficiation Fee paid by the community to Carbotura per tonne of feedstock delivered. Not a tipping fee, disposal fee, or waste charge. Confirmed at $100 CAD/tonne base for this engagement, escalating 2.5%/year.
Total Material Conversion (TMC)
The ACM platform's complete processing of a feedstock stream — from receipt through disintegration, reforming, and manufactured product output.
Waste Plan Regina (WPR)
The City of Regina's long-term solid waste management strategy, originally adopted by Council in 2011, updated 2023. The guiding document for Regina's solid waste programs and services.
§8

Sources and References

  1. 1City of Regina. Waste Plan Regina — 2023 Update. Regina.ca/waste. Retrieved March 2026.
  2. 2City of Regina. Landfill — Tipping Fees and Operations. regina.ca/home-property/recycling-garbage/landfill/. Verified October 2025 via cityrules.info.
  3. 3City of Regina. Food & Yard Waste Service. regina.ca/home-property/recycling-garbage/food-yard-waste/. Retrieved March 2026.
  4. 4City of Regina. Recycling — SK Recycles transition effective July 1, 2025. regina.ca/residents/waste/recycle/. Retrieved March 2026.
  5. 5City of Regina. Industrial, Commercial and Institutional Waste Program — bylaw requirements. Retrieved March 2026.
  6. 6EPCOR. Regina — Wastewater Treatment Plant Operations. epcor.com/ca/en/about/our-company/where-we-operate/regina.html. Retrieved March 2026.
  7. 7PPP Council of Canada. Regina Wastewater Treatment Plant Upgrade Project. pppcouncil.ca. Retrieved March 2026. Confirms EPCOR Water Services Inc. as operating entity to June 2044.
  8. 8Richter et al. (2022). Modeling of municipal waste disposal rates during COVID-19 using separated waste fraction models. PMC/NCBI. Source of 2013–2020 Regina landfill daily volume data: average 555 TPD total including C&D.
  9. 9City of Moose Jaw. Sanitary Landfill. moosejaw.ca/sanitary-landfill/. Retrieved March 2026.
  10. 10Antonio, J.G. (2025, July 29). Three potential locations for new landfill presented to Moose Jaw council. SaskToday / MooseJawToday. Retrieved March 2026. Source of 2021–2025 landfill tonnage data and $133M concept design cost.
  11. 11City of Moose Jaw Budget 2024. Landfill and waste collection fee schedule. DiscoverMooseJaw.com, December 2023. Verified tipping fee $90 CAD/tonne residential.
  12. 12CBC Saskatchewan. (2024, June 20). City of Moose Jaw forced to find new waste facility after RM rejects application. cbc.ca. Retrieved March 2026.
  13. 13CBC Saskatchewan. (2025, December 8). City of Regina signs contract with company to process organic waste. cbc.ca. Source of Awasis project and EverGen termination confirmation.
  14. 14Buffalo Pound Provincial Water Supply Commission. buffalopoundwtp.ca. Confirms service to ~260,000 persons in Regina, Moose Jaw, and corridor communities.
  15. 15Saskatchewan Waste Reduction Council (SWRC). Waste composition and composting guidance. swrc.ca. Used for organics share (~1/3) estimate applied to Moose Jaw stream.
  16. 16MooseJawToday.com. (2022, December 7). Budget 2023: New sewage lift station — AECOM engagement. Source of Moose Jaw WWTP self-operated status confirmation.
  17. 17World Population Review. Regina Population 2026; Moose Jaw Population 2026. worldpopulationreview.com. Retrieved March 2026. Population estimates.
  18. 18CBC Saskatchewan / RM of Edenwold. (2023, December). RM rejects compost facility for Regina organic waste. Source of organics processing gap context.
Was this document useful for your decision-making?
This document contains forward-looking statements based on current expectations, estimates, and projections. Actual results may differ materially from those anticipated due to factors including but not limited to: feedstock composition variability, market conditions for manufactured materials, regulatory frameworks, project-specific site conditions, and technology performance at commercial scale. All financial projections are based on RevCon™ 3 baseline assumptions and are subject to the variables described herein. Carbotura makes no guarantee of specific financial returns.